October 7, 2012
Contract on equipment unloading at “Johnson Controls”

In October 2012 contract on equipment unloading and its moving to shop at Johnson Controls was concluded.

September 27, 2012
Works on anticorrosive protection and hydro insolation at “Elopak SPb”

In September 2012 works on anticorrosive protection and hydro insolation of  SUG plant at Elopak SPb were conducted.

September 19, 2012
Works on installation of new welding line at “Gestamp Stadko”

In September 2012 works on installation of new welding line at Gestamp Stadko were carried on. Under these works there were installed equipment, as well as complex of works on laying and connection of ductwork.

September 3, 2012
Contract on changing of flexible cables at “GM” was concluded

In September 2012 contract on changing of flexible cables used for power supply and moving production equipment control in GM paint shop was concluded.

September 2, 2012
Works on elongation of preliminary preparation line at “General Motors”

During May 2012 – September 2012 at GM work on preliminary preparation line elongation were executed, including stainless steel tunnel panels supply, modification of ventilation system and installation of additional support structures and additional ducts.

September 1, 2012
Works on arrangement of dust tunnels in paint shop of “General Motors” were started

During June 2012 – September 2012 at GM works on arrangement of paint shop dust tunnels for body protection were performed.

August 21, 2012
Works on installation of new compressor at “Antolin group”

In summer 2012 works on installation of new compressor in compressed air system were executed, Antolin group, car components production.

August 19, 2012
Works on modification of metal structures in assembly shop of “Ford” manufacturing were finished

During summer shutdown at Ford manufacturing works on modification of metal structures in assembly shop and installation of protection metal structures in tanks of preliminary processing lines were executed.

August 2, 2012
Contract on arrangement of hydrofiltration system at “HMMR” had been concluded

August 2012. Contract on arrangement of hydrofiltration system in repair booth of Hyundai  assembly shop was concluded.

August 1, 2012
Works on conveyors installation in assembly shop and paint shop of “HMMR”

During two weeks of 2012 summer shutdown at Hyundai manufacturing there were executed works on design, manufacturing and installation of metals structures for conveyors in assembly and paint shops.

July 19, 2012
Installation of 4 paint robots of Sames company was executed at “Renault Avtoframos”

During 2012 summer shutdown installation of 4 paint robots of Sames company was executed, including connection to production lines, Renault Avtoframos.

July 9, 2012
Contract on arrangement of new system of body wash at “Nissan” was concluded

In July 2012 contract on arrangement of new system of body wash was concluded with Nissan manufacturing.

July 7, 2012
Contract on service of all air supply ducts was concluded with “Nissan”

In July 2012 contract on service of all air supply ducts was concluded with Nissan, including schemes compilation, duct condition investigation and issuing conclusions of exploitation term.

July 1, 2012
At own production site 2 tanks of 30 cubic meters capacity were manufactured

In July 2012 at own production site 2 tanks of 30 cubic meters capacity were manufactured, they are for production liquids used in technological processes.

June 19, 2012
Works on carry-over of gas supply ducts at “Nissan” were carried out

During summer shutdown at Nissan manufacturing works on carry-over of gas supply ducts, modification of wax application station and arrangement of  leakages collection system was concluded.

May 11, 2012
There was concluded contract on repair paint line carry-over from one shop to another at “PSMA” manufacturing in Kaluga

In May 2012 there was concluded contract on repair paint line carry-over from one shop to another at PSMA manufacturing in Kaluga. Under these works there was developed whole scope of working documents, were carried over 4 production plants, was executed whole complex of electrical works, as well as ventilation system arrangement. Also there were executed works on liquidation of existing gas supply system and arrangement of new gas supply system key ready, including confirmation with all supervising authorities.

April 3, 2012
Supply and installation of evacuation stairs at “Mobis”

April 2012. Contract on supply of evacuation stairs and other metal structures to Mobis warehouse construction site was concluded.

January 19, 2012
Contact on periodic maintenance of lifting machines at “Hyundai” was concluded

In January 2012 contact on periodic maintenance of lifting machines at Hyundai manufacturing was concluded.

January 12, 2012
During winter shut-down 2011/2012

During winter shut-down 2011/2012 (1 week) there was executed set of works on modification of metal structures of assembly shop, Hyundai Saint-Petersburg.

January 11, 2012
During winter shut-down 2011/2012

During winter shut-down 2011/2012 (1 week) were was executed set of works on modification of paint shop and assembly shop, Mobis Module CIS (bumber production), Saint-Petersburg. There were manufactured and installed metal structures, installed electrical lightning system, and executed production equipment shifting.

December 20, 2011
Started works on modification of compressor house of Kraft Foods Dirol Cadbury, Chudovo village, Leningrad region

Under the contract there must be performed works on dismantlement of old compressors, installation of new oil-free compressors. Also we connected them to electrical supply and air supply. All works must be performed by the way not to disconnect compressor house from the manufacturing more than 1.5 hour.

November 28, 2011
Started works on modification of preliminary processing line modification in paint shop, Nissan manufacturing Saint-Petersburg

Notably there must be performed change of circuital pumps, dismantlement of filters and installation of new ones, and modification of RO water distribution system.

October 3, 2011
Started works on modification of paint shop, General Motors Auto Saint-Petersburg

It includes modification of production equipment of paint shop of GM Auto, Saint-Petersburg.

September 15, 2011
Started works on manufacturing and installation of fire ladders on Hyundai manufacturing supplier’s park, Saint-Petersburg

Started works on manufacturing and installation of fire ladders on Hyundai manufacturing supplier’s park, Saint-Petersburg.

September 1, 2011
We have concluded contract with Durr Systems Rus LLC and Durr France

It includes installation of car test line in assembly shop, Peugeot manufacturing, Kaluga city. Under the contract there must be manufactured and installed metal structures – about 40 tons. Also we must install equipment, execute as-build documentation, arrange firefighting system.

August 18, 2011
During summer shut-down 2011

During summer shut-down 2011 (2 weeks, July-August) there were performed works on elongation of 3 work chambers of paint shop, elongation of oven of top paint. Al so we performed air ducts modification in paint shop of Hyundai. The Customer is Durr Korea, supervising installation and equipment supply.

August 17, 2011
During summer shut-down 2011

During summer shut-down 2011 (2 weeks, July-August) there were installed additional robots for primer application I paint shop, Hyundai saint-Petersburg. We finished complex work consisted of mechanical and electrical installation, robots connection to compressed air ducts and paint ducts. We performed the chamber elongation. The Customer was Durr Systems Rus LLC.

August 16, 2011
During summer shut-down 2011

During summer shut-down 2011 (2 weeks, July-August) there were executed complex installation of robotic machines of seal application on the car body bottom, Hyundai Saint-Petersburg. There was modified seal application booth, also we installed robots, conducted works on its connection to power supply systems and pipes of high pressure. The Customers were Hyundai Motor Manufacturing Rus and Doolim-Robotics (Korea).

August 15, 2011
During summer shut-down 2011

During summer shut-down 2011 (2 weeks, July-August) there were executed works on welding shop modification, Hyundai Saint-Petersburg. Notably there were installed 12 presses (mass of each one is 20 tons), welding robots, conveyors, welding machines. Also there were conducted equipment connection with systems of production water and compressed air. Totally there were installed about 300 tons of equipment and about 20 tons of metal structured of own manufacturing. The Customer is Hyundai Motor Manufacturing Rus, LLC.

June 15, 2011
There were started works on car repair zone modification, Hyundai Saint-Petersburg

Under the contract there must be arranged additional systems of lightning, electrical supply and air supply.

June 1, 2011
We have concluded contract with companies Durr Systems Rus (Russian representative) and Durr Limited (Great Britain) on modification of exhausting air ducts system of paint shop, Ford Motor Company in Leningrad Region.

There must be performed dismantlement of 3 chimneys (diameter: 1,5 – 2,9m, height: 28m); installation of exhausting channel from old chimneys to new one (stainless still, totally welded, app. 1200 m of welding seams); set of works on ductwork modification within paint shop. Main works on dismantlement of chimneys and installation of new exhausting ductwork must be executed during 2-weeks manufacturing shut-down.

May 30, 2011
We have concluded contract with Durr Systems Rus LLC

It includes installation of 19 by-pass pumps on the line of preliminary processing and cataphoresis application in paint shop of Hyundai Saint-Petersburg. The whole work must be performed during weekends at night shifts and day shifts.

May 15, 2011
We have concluded contract with Hyundai Motor Manufacturing Rus and Doolim-Robotics (Korea)

It includes installation of robotic body painting line in paint booths of Hyundai manufacturing in Saint-Petersburg. To fulfill the works our company must develop as-build documentation, conduct industrial safety expertise, and conduct equipment certification. Also we will manufacture and install more than 100 tons of metal structures, install more than 80 tons of equipment, including 20 paint robots. And we will perform full complex of electrical works, robots connection with compressed air ducts and paint ducts. Aside from that all 3 paint booths must be modified as well as ventilation system.

April 18, 2011
Works have been started at Peugeot car manufacturing plant, Kaluga.

Within the scope of the contract “MAD Engineering”, Co Ltd must perform installation of supporting metal structures and installation of conveyor systems in welding shop and assembly shop.

April 12, 2011
The contract between MAD Engineering, and Durr Systems Rus have been concluded for works at Ford car manufacturing plant.

The scope of the works includes dismantlement of existing chimneys in paint shop, adjustment of new chimneys as well as new technological ventilation systems.

April 4, 2011
Works at brick factory in Ryabovo village.

There were started works of oven technological ventilation systems installation and installation of other metal structures at brick factory being constructed in Ryabovo village, Leningrad region.

March 29, 2011
There were concluded contract with General Motors Auto.

There were concluded contract with General Motors Autofor designing, fabrication, installation and adjustment of safety elements of conveyor systems in paint shop.

March 20, 2011
Finished works at Donghee plant.

There were finished works on repair of heat exchange apparatus in ventilation systems of Donghee plant producing car components.

January 11, 2011
The contract between MAD Engineering and Durr Systems Rus have been concluded for works concerning of production support in paint shop of Hyundai car manufacturing plant.

Within the agreements there will be performed works on improvement of labor conditions for plant’s staff, works on safety increase, as well as repair works and production modernization works.

January 5, 2011
Contract with Magna Technoplast

Started works of existing cooling water circulation system expansion at the manufacturing plant of components for automobile industry, Magna Technoplast, Kolpino town.

December 1, 2010
Contract with Hyundai manufacturing

Concluded contract for adjustment of dedicated pipe-line of compressed high-purity air supply from paint shop to the section of car preparation at Hyundai manufacturing in Saint-Petersburg.

December 1, 2010
Contract with Hyundai manufacturing

Concluded contract for modernization of final body assembly line in welding shop of Hyundai manufacturing in Saint-Petersburg.

November 18, 2010
Contract with Unilever – Baltimor

Started works of new compressor station adjustment for food production, Unilever – Baltimor.

Within the framework of this project it is carried out equipment supply, complex of construction works, installation of equipment and pipe-lines, adjustment of ventilation system and set of works concerning of electrical installation and adjustment of compressor station automation system  with further setup of full complex.

November 15, 2010
Contract with Hyundai manufacturing

Concluded contract for modernization of different industrial systems and equipment in paint shop of Hyundai manufacturing in Saint-Petersburg.

November 1, 2010
Contract with Hyundai manufacturing

Concluded contract for modernization of line of glass insertion in the car which placed in assembly shop of Hyundai manufacturing in Saint-Petersburg.

November 1, 2010
Contract with Hyundai manufacturing

Concluded contract for soundproof chamber adjustment over equipment for car testing which placed in assembly shop of Hyundai manufacturing in Saint-Petersburg.

October 15, 2010
Contract with Hyundai manufacturing

Concluded contract for bearing construction trusses strengthening at plants – suppliers of Hyundai manufacturing in Saint-Petersburg.

October 11, 2010
Works at Hyundai manufacturing

Stared works of modernization of industrial chamber of sealer laying on car bottom side in paint shop of Hyundai manufacturing in Saint-Petersburg.

Within the framework of this project it is must be performed complex of preparation works for increase of productivity and improvement of quality of performed operations.

October 1, 2010
Works at Hyundai manufacturing

Stared works of modernization of industrial lines in welding shop of Hyundai manufacturing in Saint-Petersburg.

Within the framework of this project it is planned to install new metal structures, dismantle part of old equipment, and installed new equipment that enable shop to issue wider range of products. Particularly it is planned to install new presses, more than 30 welding robots and new systems of sealer distribution.

January 12, 2010
Modernization works at Hyundai car manufacturing plant.

Works on sound chambers installation on test line and works on glass fitting line modernization in welding shop of Hyundai car manufacturing plant are being executed.