– During summer shut-down 2011

During summer shut-down 2011 (2 weeks, July-August) there were performed works on elongation of 3 work chambers of paint shop, elongation of oven of top paint. Al so we performed air ducts modification in paint shop of Hyundai. The Customer is Durr Korea, supervising installation and equipment supply.

– During summer shut-down 2011

During summer shut-down 2011 (2 weeks, July-August) there were installed additional robots for primer application I paint shop, Hyundai saint-Petersburg. We finished complex work consisted of mechanical and electrical installation, robots connection to compressed air ducts and paint ducts. We performed the chamber elongation. The Customer was Durr Systems Rus LLC.

– During summer shut-down 2011

During summer shut-down 2011 (2 weeks, July-August) there were executed complex installation of robotic machines of seal application on the car body bottom, Hyundai Saint-Petersburg. There was modified seal application booth, also we installed robots, conducted works on its connection to power supply systems and pipes of high pressure. The Customers were Hyundai Motor Manufacturing Rus and Doolim-Robotics (Korea).

– During summer shut-down 2011

During summer shut-down 2011 (2 weeks, July-August) there were executed works on welding shop modification, Hyundai Saint-Petersburg. Notably there were installed 12 presses (mass of each one is 20 tons), welding robots, conveyors, welding machines. Also there were conducted equipment connection with systems of production water and compressed air. Totally there were installed about 300 tons of equipment and about 20 tons of metal structured of own manufacturing. The Customer is Hyundai Motor Manufacturing Rus, LLC.

– There were started works on car repair zone modification, Hyundai Saint-Petersburg

Under the contract there must be arranged additional systems of lightning, electrical supply and air supply.