August 15, 2011
During summer shut-down 2011

During summer shut-down 2011 (2 weeks, July-August) there were executed works on welding shop modification, Hyundai Saint-Petersburg. Notably there were installed 12 presses (mass of each one is 20 tons), welding robots, conveyors, welding machines. Also there were conducted equipment connection with systems of production water and compressed air. Totally there were installed about 300 tons of equipment and about 20 tons of metal structured of own manufacturing. The Customer is Hyundai Motor Manufacturing Rus, LLC.